Fairgrounds Nashville Improvement Project Update: The Week in Review: May 6-10
May 6, 2019
Construction Update
- Installation of the building envelope and canopy at Expo 1 continues.
- Steel erection for Shed 1 steel started this week and will continue into the next one.
- Framing of interior offices in Expo Buildings 1 and three is ongoing.
- Removal of soil and work to bring hardscaped ares to grade continues.
- In Expo 3, framing of doorjambs began, as did framing of restrooms and the kitchen.
- Electrical contractors worked on overhead rough ins in Expos 1 and 3.
- Also in Expos 1 and 3, masonry block is being laid.
Images
Pictured above, one of the bio-retention ponds near Fair Park. As the plants grow, they will serve to prevent erosion.
Steel erection on Shed 2 underway.
Steel erection on Shed 2 underway.
- Dark green: roofing progress
- Yellow: storm water progress
- Light green: retaining wall
- Blue: steel erection progress
- Pink: domestic water progress