Fairgrounds Nashville Improvement Project Update: The Week in Review: June 24-28

July 1, 2019

Construction Update

  • Concrete pads were poured for the condenser and metering equipment.
  • The drywall contractor is wrapping up tasks, including hanging and finishing drywall, installing door jambs and ceiling grids.
  • Installation of the storm sewer in the courtyard is ongoing.
  • Grading on the east side of the project continues as does construction of the retaining wall to the south.
  • The electrical contractor pulled wiring in Expo 1 and continued the build-out of the electrical room.
  • Base asphalt was placed at the RV park.

News Articles

Images

Expo 1 nearing completion
A view of the interior of Expo 1, nearing completion, from the mezzanine.

Expo 1 bathroom partitions
Toilets in an Expo 1 bathroom getting partitions installed.

Canopy installation
Canopy installation is ongoing at the loading dock.